General Financial Rules 2017 - Chapter 5: Works
- Works
which add capital value to existing assets but do not create new assets
are called
- Original
Works
- Repair
Works
- Minor
Works
- Contingent
Works
- New
constructions, site preparation, additions and alterations to existing
works, special repairs to newly purchased or previously abandoned
buildings or structures, including re-modelling or replacement are called
- Original
Works
- Repair
Works
- Minor
Works
- Contingent
Works
- Subject
to certain conditions a Ministry or Department at its discretion may
directly execute repair works estimated to cost up to Rupees
- 10
lakhs
- 15
lakhs
- 20
lakhs
- 30
lakhs
- A
Ministry or Department may, at its discretion, assign to any Public Works
Organisation (PWO) repair works estimated to cost above Rupees 30 Lakhs
and original/minor works of
- above
50 lakh
- above
1 crore
- above
2 crore
- any
value
- Pick
the incorrect one No works shall be commenced or liability incurred in
connection with it until
- administrative
approval has been obtained from the appropriate authority in each case.
- sanction
to incur expenditure has been obtained from the competent authority.
- a
properly detailed design has been sanctioned; while designing the
projects etc, principles of Life Cycle cost may also be considered.
- funds
to cover the charge during the year and beyond till completion of the
work have been provided by competent authority.
- State
whether true or false For purpose of approval and sanctions, a group of
works which forms one project, shall be considered as one work. Therefore,
approval or sanction of higher authority is not required as cost of each
particular work in the project is within the powers of such approval or
sanction of a lower authority.
- True
- False
- Open
tenders will be called for works costing Rupees
- 1
lakh to 10 lakh
- 2
lakh to 15 lakh
- 3
lakh to 20 lakh
- 5
lakh to 30 lakh
- Limited
tenders will be called for works costing less than Rupees
- 1
lakh
- 2
lakh
- 5
lakh
- 10
lakh
- To
review the progress of the work, the Administrative Ministry or Department
will set up a Review Committee consisting of a representative each from
the Administrative Ministry, Finance (Internal Finance Wing) and the
Executing Agency when the estimate cost of approved project is Rupees
- 50
crore and above
- 100
crore and above
- 200
crore and above
- 500
crore and above
- The
Review Committee shall have the powers to accept variation within
- 5%
of the approved estimates.
- 10%
of the approved estimates
- 10%
of the approved estimates
- 15%
of the approved estimates